Pepco Update: 1.5 Days Per Substation

In our Winter issue, we described a major RTU project at Pepco.  As of today, the team has successfully installed all nine cabinets in eight substations, the last four installations requiring only 1.5 days each.

View the complete Success Story at:

novatechweb.com/pepco

Abstract

NovaTech designed, assembled, tested and commissioned substation Remote Terminal Units (RTUs) for Potomac Electric Power Company (Pepco). This fast-track project included eight RTU assemblies, two of which were installed and commissioned just eight weeks after contract award. This award established the initial phase of Pepco’s Smart Community RTU Replacement project.